Key takeaways
- Ask every contractor for base depth in inches, aggregate type and bedding material in writing.
- A much cheaper patio quote usually has a thinner base, no fabric or stone dust bedding.
- Retaining walls above about 4 feet need engineering and usually a permit. A quote that ignores this is incomplete.
- Compare what is excluded (spoil hauling, permits, restoration) and the payment schedule, not just the total.
On this page
How do you compare two patio quotes fairly?
Put them side by side and compare the specification, not the total. A patio is mostly excavation, aggregate and compaction, and the pavers are a minority of the cost. That is why two quotes for the same footprint can differ by 40 percent: the cheaper one often proposes 3 or 4 inches of base instead of 6, skips the fabric, or beds the pavers on stone dust. You cannot see any of that after the job is done, so it has to be on paper before you sign.
If a contractor will not write down base depth, aggregate type and bedding material, you are not comparing the same product.
The line-by-line checklist
| Line item | What a complete quote says | Red flag |
|---|---|---|
| Base depth | Inches of compacted base, stated (6 for a walking patio, 8 to 10 for driveways) | "Proper base" with no number |
| Aggregate | The material named, such as 21AA crushed limestone | "Gravel" or "fill" |
| Compaction | Placed and plate-compacted in lifts (two or three for 6 inches) | Dumped full depth and compacted once |
| Geotextile | Separation fabric on the clay subgrade | Not mentioned |
| Bedding layer | About 1 inch of washed concrete sand to ASTM C33 | Stone dust or "screenings" |
| Edge restraint | Type and spike spacing (roughly 12-inch centers) | "Edging as needed" |
| Joint sand | Polymeric sand, swept and activated | Plain sand, or nothing stated |
| Wall drainage | Clean angular stone behind the wall and a drain pipe with a real outlet | Native soil backfill |
| Wall engineering | Stated when a wall exceeds about 4 feet or carries a load on top | Tall wall, no engineer, no permit |
| Permits | Who pulls them and who pays | Silence |
| Spoil and haul-off | Excavated soil removed, or where it goes | Pile left in your yard |
| Utility locate | Who calls MISS DIG 811 | Not addressed |
| Payment schedule | Deposit, progress payment, balance at completion | Most of the money before work starts |
Paver patios from $18 a square foot
Six inches of compacted 21AA over Macomb County clay, placed in lifts, with base depth, aggregate and bedding written into the quote. Every price is published on the cost guide.
Which line items matter most on Macomb County clay?
Base depth, fabric and bedding. Much of the county sits on heavy clay that holds water, and saturated clay is what frost heaves. A 6-inch base of compacted 21AA over geotextile gives water somewhere to go and keeps clay from migrating up into the stone. Stone dust bedding holds water and can pump up through the joints. Our guide to Michigan freeze-thaw and base prep explains why these three items decide how the patio looks in year three.
What should a retaining wall quote include?
A compacted leveling pad, a buried bottom course, clean drainage stone behind the block, a perforated drain pipe that discharges somewhere, compacted backfill in lifts and a glued cap. Geogrid belongs in walls whose height or load requires it. Michigan's Residential Code exempts retaining walls up to 4 feet, measured from the bottom of the footing, from a building permit unless they support a surcharge, such as a driveway or a slope above. Taller or loaded walls are engineered structures. If a quote for a 5-foot wall never mentions engineering, that is the most important line in it. See why retaining walls fail and what a retaining wall costs.
What about permits, utilities and payments?
- Permits. Ask in writing who pulls them. Rules differ by community, so check with the building department in Shelby Township, Macomb Township or wherever you live. This is general information, not legal advice.
- Utilities. Michigan law requires notice to MISS DIG 811 at least 3 business days before digging. When a contractor does the digging, the contractor makes the call.
- Payments. A modest deposit, progress payments tied to visible stages and the balance at completion is normal. Under Michigan's Construction Lien Act, you can ask a contractor for a sworn statement listing its subcontractors and suppliers, which helps you avoid paying twice if a supplier goes unpaid.
How do you use published prices to sanity-check a quote?
Use a published range to spot outliers, then use the checklist to explain them. Macomb Lawn & Snow Solutions publishes $18–$30 / sq ft for patios and $35–$65 / face ft for retaining walls, and puts base depth, aggregate type and bedding material on every quote. The hardscape cost guide lists what pushes a job to the top or bottom of a range, and the paver patio page shows the build in order. A quote far below any published range is usually missing a line from the table above.
Sources
- Mich. Admin. Code R 408.30505 (Michigan Residential Code R105.2): work exempt from permit — retaining walls up to 4 feet from bottom of footing, unless supporting a surcharge; small detached patios
- MISS DIG 811: frequently asked questions — notice at least 3 business days before digging; the party doing the work makes the call
- MCL 570.1110, Michigan Construction Lien Act: sworn statements